Prepping the floors, priming the walls, and cooling the air.

While Joe has been busy continuing window reglazing, door restoration, and plaster repair, I have been chipping away at the floors….literally. I talked a lot about the mastic tar and horse hoof glue removal process in this blog post when I was about half way through the job. Now that job is officially finished and…

Taping, mudding, scraping, and washing

One year ago this week we still hadn’t even picked up a hammer, decided on floor plan revisions, or even lined up any subcontractors.  Everything we have done since that time has been towards one big goal – drywall.  Last week our drywall was officially completed.  Let’s pause for a moment to celebrate…. Okay, time…

A better drywall experience

Week 52  (Joe) All of our drywall is now up.  It only took them 2 1/2 days to finish and (for the most part) everything went smoothly.  In my last post I commented on a couple issues that occurred after the 1st day of drywall.  The reality is that most of those issues have nothing…

Drywall finally begins

Week 52  (Joe) Amy and I spent last weekend and Monday frantically preparing for the drywall crew so that they could begin on Tuesday.  The big day finally arrived and we drove home after work like a couple of kids on Christmas morning.  Except…  there was nothing under the tree.  Sadly, no drywall.  The drywall…